Perbaikan Turap Kali Baru Timur Capai 85 Persen

Kali Baru Timur Channel's Retaining Wall Repair Reaches 85 Percent

Kali Baru Timur Channel's retaining wall repair on Jalan Permata RW 06, Kampung Melayu, Jatinegara, East Jakarta, has reached 85 percent to complete. This repair is targeted to finish by the end of February.

Our target is to complete this repair in the end of February

This involves at least 20 Water Resources (SDA) Unit personnel and long arm unit to repair it. On the location, personnel installed river stones and reinforced concrete or sloof to strengthen its foundation.

Jatinegara SDA Unit Staff, Tarmizal mentioned, this retaining wall was collapsed on January 2nd because of high intensity of rain.

SDA Repairs PHB's Retaining Wall on Jl. Pemuda

"From that day, we repair it as soon as possible. Our target is to complete this repair in the end of February," he asserted, Wednesday (2/19).

Due to its height of 10 meters and length of 47 meters, he admitted, it takes quite a long time to repair it. Besides, Kali Baru Timur Channel is connected directly to Ciliwung River in Jatinegara.

Linked News
Popular News indeks
  1. Volcanic Ash Reaches Jakarta, Health Agency Calls for Protective Measures

    access_time06-09-2026 remove_red_eye1653 personBudhi Firmansyah Surapati
  2. BMKG: Sunny to Cloudy Skies Forecast Across Jakarta Today

    access_time11-09-2026 remove_red_eye1505 personDessy Suciati
  3. Jakartans Urged to Stay Calm and Take Precautions Amid Mt. Anak Krakatau Volcanic Ash

    access_time06-09-2026 remove_red_eye836 personBudhi Firmansyah Surapati
  4. Jakarta Provincial Government Anticipates the Impact of Volcanic Ash from Mount Anak Krakatau

    access_time06-09-2026 remove_red_eye691 personFolmer
  5. Jakarta Reallocates Funds for Rp 250M Suckermouth Catfish Study After Pramono’s Direct Order

    access_time10-09-2026 remove_red_eye655 personFakhrizal Fakhri