Atasi Genagan di Jalan Patra, Saluran di Normalisasi

Channels Normalization on Jalan Patra and Mangga I Reaches 55 Percent

Until now it has reached 55 percent ongoing and is targeted to be complete on October 15

The water channels normalization work on Jalan Patra and Jalan Mangga I, Duri Kepa, Kebon Jeruk, West Jakarta has reached 55 percent.

West Jakarta Water Resources (SDA) Sub-agency's Development and Drainage Improvement Division Head Imam Prasetyo said it had been ongoing since October 22.

Rawa Lindung Reservoir Dredged from Waste

He explained, the channel normalization on Jalan Patra was up to 325 meters length with 150 centimeters depth and width. Then on Jalan Mangga I, it was done up to 145 meters with 80 centimeters width and depth.

"Until now it has reached 55 percent ongoing and is targeted to be complete on October 15," he said, Wednesday (11/11).

It was done to maximize water holding capacity and to smoothen water flow into retention pond or locally known as olakan towards Sekretaris River when rain poured.

"By so we can avoid puddles on Jalan Patra, Jalan Asem, Jalan Mangga and its surroudings," he closed.

Linked News
Popular News indeks
  1. Nighttime Surveillance on Railroad Banks of Jalan I Gusti Ngurah Rai Intensified

    access_time08-05-2026 remove_red_eye2636 personNurito
  2. Closure of Railway Level Crossings Socialized

    access_time13-05-2026 remove_red_eye2369 personTiyo Surya Sakti
  3. Governor Pram Appreciates Residents for Keeping Jakarta Safe and Comfortable

    access_time09-05-2026 remove_red_eye981 personFolmer
  4. Telkomsel Digiland Run 2026 Parking Lot List: Check Now!

    access_time14-05-2026 remove_red_eye977 personAldi Geri Lumban Tobing
  5. Waste Sorting Movement Boosts Circular Economy

    access_time12-05-2026 remove_red_eye847 personFakhrizal Fakhri