Pembangunan Waduk Mini di Ceger Capai 80 Persen

Mini Reservoir Development in Ceger Has Touched 80 Percent

We aim to finish it in two weeks

The 970-square-meter long mini reservoir development work on Jalan SMPN 160, RT 02/05 Ceger, Cipayung, East Jakarta has touched 80 percent.

Cipayung Sub-district Head Fajar Eko Satrio said the development work had been ongoing since a month. It was conducted manually by 20 personnel of the Water Resources (SDA) Task Force and PPSU.

Collapsed Sheet Pile and Reservoir in Kramat Jati Being Repaired

According to him, the reservoir was done to overcome the inundation in the surrounding residential areas due to the existing drainage channels unable to accommodate water.

"We aim to finish it in two weeks," he said, Wednesday (1/27).

Nevertheless, the reservoir was able to accommodate overflowing waters of the existing drainage channels in residential areas.

"To function it optimally, we also build an infiltration well near the reservoir," he said.

Linked News
Popular News indeks
  1. Pramono Pushes to Complete Long-Delayed Pluit JLNT by March 2027

    access_time20-11-2026 remove_red_eye695 personDessy Suciati
  2. JAF 2026 Highlights Maritime Heritage and Coastal Architecture

    access_time21-11-2026 remove_red_eye677 personAnita Karyati
  3. Hosted in Sydney, Pramono Discusses Opening Australian Campuses in Jakarta

    access_time25-11-2026 remove_red_eye652 personDessy Suciati
  4. Jakarta Strengthens ASEAN Cooperation on Climate, Transport, and Youth

    access_time20-11-2026 remove_red_eye637 personFolmer
  5. BORJU Markets 200 Local Products

    access_time20-11-2026 remove_red_eye603 personAnita Karyati