Pengerjaan Embung Flamboyan Capai 30 Persen

Flamboyan Embung Project Work in Cengkareng Accelerated

The West Jakarta Water Resources (SDA) Sub-agency continues to speed up the Flamboyan Embung (artificial lake) development on Jalan Jaya No. 25, Cengkareng Sub-district. Thus far the development itself has touched 30 percent.

It has been carried out since February 19 and is targeted to be complete in the upcoming May

Drainage Maintenance Division Head Wawan Kurniawan said, to conduct it, as many as eight personnel plus two excavators type amphibious AK 12 and landline.

"It has been carried out since February 19 and is targeted to be complete in the upcoming May," he expressed, Friday (4/9).

Rawa Malang Embung Construction Has Touched 40 Percent

He explained the embung was built to minimize flooding when heavy rain poured the city.

"Our hope is it is able to accommodate rainwater in large quantities. After this, we intend to build a water channel that connects embung to the Palem connecting channel," he explained.

He was also conducting data collection to ascertain the location of the pump, data collection for the lowest channel and so forth.

He added the total land area in the area was 7,070 square meters, where 5,000 square meters would be made of embung and the rest would be built supporting facilities such as jogging tracks, futsal courts, etc. The embung itself would be dredged to 3.5 meters depth.

"Hopefully we can maximally overcome the flood issues in the area," he hoped.

Linked News
Popular News indeks
  1. Jakarta Council Begins Deliberations on New Population and Housing Bylaws

    access_time21-08-2026 remove_red_eye1885 personFakhrizal Fakhri
  2. Pramono Vows to Prioritize Jakarta’s Strategic Development

    access_time22-08-2026 remove_red_eye850 personDessy Suciati
  3. Pramono Commends Madurese Community for Their Vital Role in Building Jakarta

    access_time19-08-2026 remove_red_eye681 personDessy Suciati
  4. New LRT Jakarta Route Set for Official Launch on August 26

    access_time22-08-2026 remove_red_eye447 personDessy Suciati
  5. Jakarta Agrees on Rp79.59T Revised 2026 Budget Framework

    access_time21-08-2026 remove_red_eye428 personFakhrizal Fakhri