3.000 Karung Lumpur Diangkut dari Jl Raya Ahmad Yani

3,000 Sacks of Mud Collected from Dredging Work on Jl. Raya Ahmad Yani

Total 3,000 sacks full of mud which collected from connection (Phb) channel on Jl. Ahmad Yani, East Jakarta were transported by Matraman Sub-district Water Resources (SDA) Unit on Tuesday (5/11).

In total, we have transported 3,000 sacks from Jl. Ahmad Yani for the past two days

Matraman Sub-district SDA Unit Coordinator, Agus Sutono explained, his side dredged mud in 7 points along Jl. Ahmad Yani. It started from Utan Kayu Intersection to in front of SMKN 5 Kebon Sereh. This dredging work was carried out from Monday (5/11) to Tuesday (5/11).

"In total, we have transported 3,000 sacks from Jl. Ahmad Yani for the past two days. The dredging work involves 50 Matraman SDA Unit personnel," he informed.

Mud Dredging on Jl. Kaca Jendela II will Be Completed in The Next Two Months

Because Wednesday (5/12) has entered joint leave period, he added, dredging work will be continued next week or after Eid al-Fitri 1442 Hijr holiday.

"Mud that we have dredged from the channel will be disposed to Cakung East Flood Canal (KBT) Sandtrap area," he mentioned.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1591 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1441 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1307 personFolmer
  4. Pramono Inaugurates Mayapada Hospital to Improve Healthcare Services

    access_time09-07-2026 remove_red_eye968 personDessy Suciati
  5. MRT Phase 2A Northbound Tunnel Excavation Completed

    access_time09-07-2026 remove_red_eye845 personAldi Geri Lumban Tobing