Penanganan Genangan di Jalan Pangeran Jayakarta Terus Dituntaskan
....
photo istimewa - Beritajakarta.id

Flood Handling Work on Jalan Pangeran Jayakarta is Accelerated

Flood handling work on Jalan Pangeran Jayakarta, Mangga Dua Selatan Urban Village, Sawah Besar, Central Jakarta, is accelerated until the end of this year.

The purpose to build retention basin is to hold water when heavy rain falls

Central Jakarta Assistant for Economic and Development, Bakwan Ferizan Ginting said, after constructing retention basin (embung) as wide as 600 square meters which completed in early May, Jakarta Water Resources (SDA) Agency will build a crossing that connects retention basin with Ciliwung River's tributary.

"We will build crossing channel on Jalan Pangeran Jayakarta to connect retention basin with Ciliwung River's tributary," he mentioned, Wednesday (5/26).

Central Jakarta will Build Green Open Space in ITC Cempaka Mas

He is optimistic that retention basin and channel crossing construction will solve flood problems on Jalan Pangeran Jayakarta.

"The purpose to build retention basin is to hold water when heavy rain falls. Later on, retention basin will be drained out to Ciliwung River's tributary," he explained.

Linked News
Popular News indeks
  1. Three South Jakarta Parks Set for Revitalization and 24-Hour Operation

    access_time12-04-2025 remove_red_eye457 personDessy Suciati
  2. 60 Joint Personnel Conduct Community Work in Karet Tengsin

    access_time13-04-2025 remove_red_eye395 personBudhi Firmansyah Surapati
  3. Free Transportation Services to Facilitate Residents' Mobility

    access_time17-04-2025 remove_red_eye286 personDessy Suciati
  4. Jakarta to be Designed as a Film City

    access_time13-04-2025 remove_red_eye276 personFakhrizal Fakhri
  5. BTN Jakarta International Marathon 2025, Be There!

    access_time14-04-2025 remove_red_eye247 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik