End of November, Cibubur Bridge Construction Completed
Reported by Nurito | Translated by Nugroho Adibrata
Our completion target is in November 2022
The Cibubur Bridge construction on Jalan Raya Lapangan Tembak, Cibubur, Ciracas, East Jakarta has touched 83.78 percent.
East Jakarta Bina Marga Sub-agency's Road and Bridge Division Head, Budi Cahyo Wardoyo explained the work is in the stage of trimming the arch railings, sidewalks, and bridge bodies. When finished, it would be continued with the installation of the words Cibubur and Pekayon using acrylic attached to the railing.
Sky Bridge Construction on Jalan Kebon Kacang Being Finalized"Our completion target is in November 2022," he said, Friday (11/4).
After it was done, he explained, the bridge would be asphalted with hotmix method. While the sidewalk would be painted and the body of the bridge painted white and brown like wood.
He added that the bridge that spans the Cipinang River has 14 meters long. On the left and right sides, there will be a pedestrian walkway as wide as 80 to 100 centimeters.
"We also widen the bridge from 6.7 to 10.9 meters, including the bridge body about one meter high compared to the previous condition," he concluded.