Pembangunan Jembatan Cibubur Capai 83,78 persen

End of November, Cibubur Bridge Construction Completed

Our completion target is in November 2022

The Cibubur Bridge construction on Jalan Raya Lapangan Tembak, Cibubur, Ciracas, East Jakarta has touched 83.78 percent.

East Jakarta Bina Marga Sub-agency's Road and Bridge Division Head, Budi Cahyo Wardoyo explained the work is in the stage of trimming the arch railings, sidewalks, and bridge bodies. When finished, it would be continued with the installation of the words Cibubur and Pekayon using acrylic attached to the railing.

Sky Bridge Construction on Jalan Kebon Kacang Being Finalized

"Our completion target is in November 2022," he said, Friday (11/4).

After it was done, he explained, the bridge would be asphalted with hotmix method. While the sidewalk would be painted and the body of the bridge painted white and brown like wood.

He added that the bridge that spans the Cipinang River has 14 meters long. On the left and right sides, there will be a pedestrian walkway as wide as 80 to 100 centimeters.

"We also widen the bridge from 6.7 to 10.9 meters, including the bridge body about one meter high compared to the previous condition," he concluded.

Linked News
Popular News indeks
  1. Jakarta Govt-City Council Step Up Coordination to Address Key Urban Challenges

    access_time22-02-2026 remove_red_eye1417 personFakhrizal Fakhri
  2. Free Transit Card Applications Skyrocket 143%, Passing 76k Mark

    access_time20-02-2026 remove_red_eye1037 personAldi Geri Lumban Tobing
  3. CNY 2577 Kongzili: Matakin Calls for Justice and Solidarity

    access_time22-02-2026 remove_red_eye882 personAldi Geri Lumban Tobing
  4. BPBD Issues Alert Over Tidal Flooding in 12 Jakarta Coastal Areas

    access_time25-02-2026 remove_red_eye853 personAldi Geri Lumban Tobing
  5. Free Tattoo Removal at Sunda Kelapa Mosque Targets 100 Residents

    access_time24-02-2026 remove_red_eye838 personFolmer