Pembangunan Jembatan Jembatan Antar Kampung di Jalan H. Montong Ciganjur Capai 90 Persen

July 13, Bridge Between Villages Construction on Jalan H. Montong Completed

The bridge between villages construction located on Jalan H. Montong, RW 02 Ciganjur, Jagakarsa, South Jakarta, which has been underway since May 9 is targeted to be completed by July 13.

The progress of the bridge construction has reached 90 percent

South Jakarta Bina Marga Sub-agency's Road and Bridge Division Head, Agus Indroyono said that the construction progress has entered the casting stage of the bridge floor plates using conventional concrete.

It would take a maximum of 28 days to make the concrete floor of the bridge more sturdy and durable.

Lampiri Bridge in Pondok Kelapa Transformed Into Community Interaction Space

"The progress of the bridge construction has reached 90 percent," he expressed, Wednesday (7/6).

After it was complete, it would be continued with the ramp casting for the transition from the road to the bridge. While the raling has been installed first using gafanis iron.

"The bridge body is one meter higher than the initial condition. We are targeting construction to be completed on target," he stated.

Linked News
Popular News indeks
  1. Central Jakarta Administration Acts Swiftly to Handle Kebon Kosong Fire

    access_time02-06-2026 remove_red_eye1458 personFolmer
  2. Public Urged to Use Public Transit for GBK Events to Avoid Heavy Traffic

    access_time05-06-2026 remove_red_eye1254 personAldi Geri Lumban Tobing
  3. Traffic Measures Prepared to Ease Congestion Around GBK This Weekend

    access_time04-06-2026 remove_red_eye1147 personAldi Geri Lumban Tobing
  4. Central Jakarta Government Responds Quickly to Fire Victims in Tanah Tinggi

    access_time04-06-2026 remove_red_eye1002 personFolmer
  5. Jakarta Waives Motor Vehicle Tax Fines and Title Transfer Fees

    access_time01-06-2026 remove_red_eye894 personAldi Geri Lumban Tobing