End of January, Channel Normalization in Cilangkap Completed

The construction of the 47-meter-long channel in the residential area of Jalan Lindung, Gg Pelita, RT 01/0 Cilangkap, Cipayung, East Jakarta is being accelerated.

The work progress has touched 60 percent

Cipayung Sub-district Water Resources (SDA) Executing Unit Head, Dian Kartika stated the normalization involved eight personnel has been ongoing since three weeks and is targeted for completion in two weeks ahead.

"The work progress has touched 60 percent," she expressed, Wednesday (1/8).

Four Channels in Sawah Besar Normalized

According to her, the channel was normalized to optimize the channel's function in accommodating water in large quantities.

"It is done using 65x65-centimeter U-ditch concrete to accommodate maximum water," she explained.

The work received appreciation from locals, as it is the aspiration they proposed in the Musrenbang 2022.

RW 04 Chairman, Sugito stated that prior to normalization, the area was often flooded in the rainy season with 20 centimeters high.

"Hopefully, it can minimize flooding when it rains," he hoped.

Linked News
Popular News indeks
  1. Kramat Pulo Fire Survivors Get Help Replacing School Documents

    access_time09-10-2026 remove_red_eye476 personFolmer
  2. New Kelapa Gading-Pulogadung Road to Ease Traffic and Improve Access

    access_time10-10-2026 remove_red_eye467 personAldi Geri Lumban Tobing
  3. Jakarta Administration Steps Up Proactive Fire Prevention Efforts

    access_time09-10-2026 remove_red_eye463 personDessy Suciati
  4. Basic Supplies Distributed to Pinang Ranti Fire Survivors

    access_time09-10-2026 remove_red_eye458 personNurito
  5. North Jakarta PPAPP Promotes SIDAYA to Improve Seniors' Quality of Life

    access_time09-10-2026 remove_red_eye458 personAnita Karyati