End of January, Channel Normalization in Cilangkap Completed

The construction of the 47-meter-long channel in the residential area of Jalan Lindung, Gg Pelita, RT 01/0 Cilangkap, Cipayung, East Jakarta is being accelerated.

The work progress has touched 60 percent

Cipayung Sub-district Water Resources (SDA) Executing Unit Head, Dian Kartika stated the normalization involved eight personnel has been ongoing since three weeks and is targeted for completion in two weeks ahead.

"The work progress has touched 60 percent," she expressed, Wednesday (1/8).

Four Channels in Sawah Besar Normalized

According to her, the channel was normalized to optimize the channel's function in accommodating water in large quantities.

"It is done using 65x65-centimeter U-ditch concrete to accommodate maximum water," she explained.

The work received appreciation from locals, as it is the aspiration they proposed in the Musrenbang 2022.

RW 04 Chairman, Sugito stated that prior to normalization, the area was often flooded in the rainy season with 20 centimeters high.

"Hopefully, it can minimize flooding when it rains," he hoped.

Linked News
Popular News indeks
  1. Pramono Pushes to Complete Long-Delayed Pluit JLNT by March 2027

    access_time20-11-2026 remove_red_eye640 personDessy Suciati
  2. JAF 2026 Highlights Maritime Heritage and Coastal Architecture

    access_time21-11-2026 remove_red_eye617 personAnita Karyati
  3. Jakarta Strengthens ASEAN Cooperation on Climate, Transport, and Youth

    access_time20-11-2026 remove_red_eye596 personFolmer
  4. BORJU Markets 200 Local Products

    access_time20-11-2026 remove_red_eye557 personAnita Karyati
  5. Jakarta Hosts 2026 UCWDC Asian Championship with 280 Dancers from Five Countries

    access_time20-11-2026 remove_red_eye543 personBudhi Firmansyah Surapati