You don't have javascript enabled. Good luck with that.
Pencarian
Warga Apresiasi Normalisasi Saluran Air di Cilangkap

End of January, Channel Normalization in Cilangkap Completed

The construction of the 47-meter-long channel in the residential area of Jalan Lindung, Gg Pelita, RT 01/0 Cilangkap, Cipayung, East Jakarta is being accelerated.

The work progress has touched 60 percent

Cipayung Sub-district Water Resources (SDA) Executing Unit Head, Dian Kartika stated the normalization involved eight personnel has been ongoing since three weeks and is targeted for completion in two weeks ahead.

"The work progress has touched 60 percent," she expressed, Wednesday (1/8).

Four Channels in Sawah Besar Normalized

According to her, the channel was normalized to optimize the channel's function in accommodating water in large quantities.

"It is done using 65x65-centimeter U-ditch concrete to accommodate maximum water," she explained.

The work received appreciation from locals, as it is the aspiration they proposed in the Musrenbang 2022.

RW 04 Chairman, Sugito stated that prior to normalization, the area was often flooded in the rainy season with 20 centimeters high.

"Hopefully, it can minimize flooding when it rains," he hoped.

Linked News
Popular News indeks
  1. Commission E Enlists Religious Leaders to Fight Drugs and Violence

    access_time24-07-2026 remove_red_eye1278 personFakhrizal Fakhri
  2. Jakarta Government Prepares Rp 249 B to Renovate Four Schools

    access_time25-07-2026 remove_red_eye861 personDessy Suciati
  3. 20 Shade Trees Planted on Jalan Komodor Halim Perdanakusuma

    access_time24-07-2026 remove_red_eye797 personNurito
  4. Transjakarta Officially Commences Jakarta Batavia Open-Top Bus Service

    access_time24-07-2026 remove_red_eye794 personBudhi Firmansyah Surapati
  5. Rano Urges Jakarta Scouts to Be Active in Waste Sorting Movement

    access_time25-07-2026 remove_red_eye664 personAldi Geri Lumban Tobing