End of January, Channel Normalization in Cilangkap Completed

The construction of the 47-meter-long channel in the residential area of Jalan Lindung, Gg Pelita, RT 01/0 Cilangkap, Cipayung, East Jakarta is being accelerated.

The work progress has touched 60 percent

Cipayung Sub-district Water Resources (SDA) Executing Unit Head, Dian Kartika stated the normalization involved eight personnel has been ongoing since three weeks and is targeted for completion in two weeks ahead.

"The work progress has touched 60 percent," she expressed, Wednesday (1/8).

Four Channels in Sawah Besar Normalized

According to her, the channel was normalized to optimize the channel's function in accommodating water in large quantities.

"It is done using 65x65-centimeter U-ditch concrete to accommodate maximum water," she explained.

The work received appreciation from locals, as it is the aspiration they proposed in the Musrenbang 2022.

RW 04 Chairman, Sugito stated that prior to normalization, the area was often flooded in the rainy season with 20 centimeters high.

"Hopefully, it can minimize flooding when it rains," he hoped.

Linked News
Popular News indeks
  1. Commission D Legislator Supports Park Monitoring Optimization

    access_time20-01-2025 remove_red_eye1500 personDessy Suciati
  2. Realizing Food Self-Sufficiency, Jakarta Holds Simultaneous Planting Activity

    access_time21-01-2025 remove_red_eye918 personAldi Geri Lumban Tobing
  3. Residents Flock to Cheap Bazaar at Cilandak Timur Urban Village Office

    access_time15-01-2025 remove_red_eye770 personTiyo Surya Sakti
  4. City and Kejati Forge Cooperation for Good Government Governance

    access_time21-01-2025 remove_red_eye383 personFolmer
  5. 13 Inter-village Bridges in South Jakarta Revitalized

    access_time16-01-2025 remove_red_eye363 personTiyo Surya Sakti