C. Jakarta Bina Marga Sub-dept. Accelerates Sidewalk Maintenance
Reported by Wuri Setyaningsih | Translated by Maria Inggita
Central Jakarta Bina Marga Sub-dept. accelerates sidewalk maintenance in eight sub-districts. It is targeted to complete by the end of November.
In total, 48,299 square meters sidewalk is in maintenance progress
"All contracts are targeted to finish on November 30. I am optimistic these can be done on time," said Sukowibowo, Head of Central Jakarta Bina Marga Sub-dept., Tuesday (10/10).
From Central Jakarta Bina Marga Sub-dept. information, sidewalk maintenance in Cempaka Putih Sub-district is done in four points; on Jl. Cempaka Putih Tengah 1, Jl. Cempaka Putih Tengah 2, and Jl. Cempaka Putih Tengah 3.
Daan Mogot Pedestrian Arrangement Has Touched 54 Percent"Progress in Cempaka Putih reaches 45 percent. While in Johar Baru on Jalan Percetakan Negara reaches 65 percent," he added.
In Gambir Sub-district on Jl. AM. Sangaji has reached 60 percent. There are also three points in Tanah Abang Sub-district on Jl. Kebon Jati, Jl. Fachrudin, and Jl. Wahid Hasyim which progress has reached 40 percent.
In Kemayoran Sub-district on Jl. Bungur Besar Raya has reached 45 percent, in Sawah Besar Sub-district on Jl. Karanganyar Raya has reached 75 percent, while for Jl. Pos and Jl. Suratmo has reached 37 percent.
"In total, 48,299 square meters sidewalk is in m
aintenance progress," he closed.