Progress Pengerukan Waduk Ria Rio Capai 40 Persen

Mud Dredging in Ria Rio Reservoir Has Reached 40 Percent

It is also carried out to minimize flooding on Jalan Perintis Kemerdekaan and residential areas in Kayu Putih

The mud dredging process in the Ria Rio Reservoir that has been ongoing since last February has reached 40 percent.

Every day, seven heavy equipments are deployed to dredge the reservoir, which covers about eight hectares with approximately six meters depth.

Pulo Mas Jaya to Revitalize Ria Rio Reservoir

East Jakarta Water Resources (SDA) Sub-agency's Maintenance Division Head Puryanto said that dredging was done to accommodate water in large quantities when rain pours.

"It is also carried out to minimize flooding on Jalan Perintis Kemerdekaan and residential areas in Kayu Putih," he said, Wednesday (6/10).

He added it was actually targeted to be completed within four months but impossible due to COVID-19.

"So we target it at least by the end of this year," he closed.

Linked News
Popular News indeks
  1. City Council Strengthens Synergy with Central Legislators to Support Jakarta`s Development

    access_time30-07-2026 remove_red_eye1039 personFakhrizal Fakhri
  2. Jakarta Government Prepares Rp 249 B to Renovate Four Schools

    access_time25-07-2026 remove_red_eye877 personDessy Suciati
  3. Rano Urges Jakarta Scouts to Be Active in Waste Sorting Movement

    access_time25-07-2026 remove_red_eye691 personAldi Geri Lumban Tobing
  4. Pramono Encourages Residents to Stay Active at Rasuna Said CFD

    access_time26-07-2026 remove_red_eye622 personFolmer
  5. Jakarta Steps Up Food Waste Prevention

    access_time25-07-2026 remove_red_eye572 personAldi Geri Lumban Tobing