Progress Pengerukan Waduk Ria Rio Capai 40 Persen

Mud Dredging in Ria Rio Reservoir Has Reached 40 Percent

It is also carried out to minimize flooding on Jalan Perintis Kemerdekaan and residential areas in Kayu Putih

The mud dredging process in the Ria Rio Reservoir that has been ongoing since last February has reached 40 percent.

Every day, seven heavy equipments are deployed to dredge the reservoir, which covers about eight hectares with approximately six meters depth.

Pulo Mas Jaya to Revitalize Ria Rio Reservoir

East Jakarta Water Resources (SDA) Sub-agency's Maintenance Division Head Puryanto said that dredging was done to accommodate water in large quantities when rain pours.

"It is also carried out to minimize flooding on Jalan Perintis Kemerdekaan and residential areas in Kayu Putih," he said, Wednesday (6/10).

He added it was actually targeted to be completed within four months but impossible due to COVID-19.

"So we target it at least by the end of this year," he closed.

Linked News
Popular News indeks
  1. Jalan Kebon Kelapa I Repaved

    access_time07-07-2026 remove_red_eye1034 personNurito
  2. Jakarta KPU Records More Than 8.2 Million Registered Voters

    access_time06-07-2026 remove_red_eye961 personFolmer
  3. Pramono Inaugurates Mayapada Hospital to Improve Healthcare Services

    access_time09-07-2026 remove_red_eye911 personDessy Suciati
  4. MRT Phase 2A Northbound Tunnel Excavation Completed

    access_time09-07-2026 remove_red_eye734 personAldi Geri Lumban Tobing
  5. Addressing Collapsed Road in Pulo Gadung is a Priority, Pramono Says

    access_time08-07-2026 remove_red_eye695 personDessy Suciati