Pulogebang Terminal's Flyover Construction Stagnated

The flyover construction which will be an exit-enter access for the bus connecting the Sentra Timur Pulo Gebang's Integrated Bus Terminal Pulo and Jakarta Outer Ring Road (JORR)'s toll road, is predicted will be delayed.

Our initial plan, the flyover can be completed at the end of December this year. But its construction will be delayed due to land acquisition problem

This is because, people whose lands affected by the project are complaining to the offer of compensation from Jakarta Provincial Government.

"Our initial plan, the flyover can be completed at the end of December this year. But its construction will be delayed due to land acquisition problem," said Head of multi-level intersection division for Jakarta Public Works (DPU), Heru Suwondo, Tuesday (10/14).

Bad Smell, Citizens Demand Septic Tank Factory in Pulogebang Closed Down

Suwondo explained citizens reject the taxable value of property (NJOP) offered by the East Jakarta Administration's Land Procurement Committee (P2T). The flyover itself would be made up to 1 km.

"The flyover is built as terminal access, and I hope it can be supported by locals," he expressed.

According to him, before the construction, terminal access from and to JORR toll road will use another toll road on the east side of terminal. It will be used as access toward Cakung 1 and Cakung 2 toll road Gates.

As known, some public transports that have begun to be served by such terminal are Transjakarta bus plying corridor XI (Kampung Melayu-Pulo Gebang), KWK T22 (Pulogadung Terminal-Pulo Gebang), KWK T25 (Rawamangun-Pulo Gebang) and KWK T29 (Pulogadung-Gudang Palad).

Linked News
Popular News indeks
  1. Transjakarta Resumes Operations with Strategic Service Adjustments

    access_time28-08-2026 remove_red_eye891 personAldi Geri Lumban Tobing
  2. Jakarta Deploys 120 Personnel to Counteract Traffic Disruption for Today’s Protests

    access_time27-08-2026 remove_red_eye804 personAldi Geri Lumban Tobing
  3. JIF Summit 2026 Drives Global Partnerships and Investment Growth in Jakarta

    access_time28-08-2026 remove_red_eye633 personAldi Geri Lumban Tobing
  4. Drainage Normalization on Jalan Mandioli to Be Completed in October

    access_time28-08-2026 remove_red_eye470 personFolmer
  5. Transjakarta Commits to Accelerating Modal Integration and Fleet Electrification

    access_time31-08-2026 remove_red_eye457 personAldi Geri Lumban Tobing