The Kali Gongseng River Bridge repair work in the border area of RW 06 and 07, Cijantung Urban Village, Pasar Rebo, East Jakarta has touched 70 percent.

It is targeted to be complete for two weeks ahead,"

East Jakarta Bina Marga Sub-agency's Road and Bridge Division Head, Ilham Raya expressed the bridge as long as 8 meters and 3.5 meters width was under repair, as the position was very low. As a result, a lot of garbage was stuck in the bridge when heavy rain poured and caused inundation in the residential area. The bridge was seen being demolished and rebuilt higher than before.

"To conduct it, eight personnel have been deployed to install the bridge's floor plate (habim iron) and bordes plate. The bridge frame made of iron has also been neatly installed," he said.

18 Bridges Beautified in Menteng and Cempaka Putih

He ensured that there were no technical problems in the field, but only access to its location which was narrow and winding.

"It is targeted to be complete for two weeks ahead," he stated.

Linked News
Popular News indeks
  1. Jakarta Council Begins Deliberations on New Population and Housing Bylaws

    access_time21-08-2026 remove_red_eye1931 personFakhrizal Fakhri
  2. Pramono Vows to Prioritize Jakarta’s Strategic Development

    access_time22-08-2026 remove_red_eye1016 personDessy Suciati
  3. Rano: CIEIE 2026 to Catapult Jakarta’s MSMEs onto the International Stage

    access_time25-08-2026 remove_red_eye716 personBudhi Firmansyah Surapati
  4. Pramono Pushes for Partnership Between New Toto Tentrem and Tarakan Hospitals

    access_time24-08-2026 remove_red_eye636 personDessy Suciati
  5. New LRT Jakarta Route Set for Official Launch on August 26

    access_time22-08-2026 remove_red_eye495 personDessy Suciati