By End of February, Channel Dredging on Jalan Pegangsaan Dua Completed

We send 12 workers to the location every day

The North Jakarta Water Resources (SDA) Sub-agency is seen dredging the water channel on Jalan Pegangsaan Dua, RW 03 Pegangsaan Dua Urban Village, Kelapa Gading. It has been carried out since November 3, 2022 and is targeted to be completed by the end of this month.

Kelapa Gading Sub-agency SDA Executing Unit Head, Citrin Indarwati the water channel on Jalan Pegangsaan Dua has a total length of 2,300 meters and a width of 80 to 100 centimeters. This dredging work is carried out to anticipate inundation in the Kelapa Gading Door 3 traffic light area.

Next Week, Channel Dredging in Kayu Manis Completed

According to her, the traffic light area to the Green Hill Apartment is always flooded to a height of more than 15 centimeters when heavy rain occurs.

"After being checked, the channel was strewn by mud, garbage, tree roots, and building debris," she said, Thursday (2/2).

She explained that the stream from the channel on the road connects to the Kelapa Hibrida Connecting Channel and then flows into Betik and Sunter rivers before ending in the sea. As a result, the channel could not accommodate water optimally, thus the water clogged and spilled out into the road.

"It is focused on both sides of the channel, where each has 1,150 meters long. So, the total length of the drainage work is around 2,300 meters," she explained.

Technically, the work was divided into two segments. That was the first segment covering the east side of the 1,150-meter-long channel which started from November 3 to December 16, 2022 and the second segment on the west side has been underway since December 19, 2022, until now.

"We send 12 workers to the location every day. Our completion target of this work is by the end of this February," she asserted.

RT 04/03 Pegangsaan Dua Urban Village Chairman, Parid hoped that the dredging could be maximized and quickly completed for zero inundation.

"Hopefully, it can be finished soon. All this time, if moderate intensity rain occurs for more than 30 minutes, it has caused inundation," he stated.

Linked News
Popular News indeks
  1. Temporary Crosswalk to Be Built at Tendean Pedestrian Bridge Site

    access_time18-07-2026 remove_red_eye1776 personFakhrizal Fakhri
  2. China-Based Training Equips PR Professionals and Journalists for Digital Media Transformation

    access_time19-07-2026 remove_red_eye1539 personFakhrizal Fakhri
  3. Jakarta Supports Social Media Restrictions for Children

    access_time20-07-2026 remove_red_eye1124 personFakhrizal Fakhri
  4. Rano Challenges Jakarta Provoke Organizers to Hold Exhibition Along Sudirman-Thamrin

    access_time18-07-2026 remove_red_eye1106 personBudhi Firmansyah Surapati
  5. Gas Stove Leak Sparks Fire, Gutting Five Rented Houses on Jalan Kayu Tinggi

    access_time17-07-2026 remove_red_eye1008 personNurito