Basuki : Proyek MRT Terlambat Kena Denda Ratusan Miliar
"Pembangunan MRT kalau terlambat satu bulan, kita bisa rugi sekitar Rp 500 miliar. Cost nya bisa tambah. Kita targetkan proyek ini rampung 2018 mendatang," kata Pelaksana Tugas (Plt) Gubernur DKI Jakarta, Basuki T Purnama usai rapat monitoring perce.
photo Yopie Oscar - Beritajakarta.id

Land Acquisition Disturbed MRT Project

Mass Rapid Transit (MRT) project in the city meets problem. Affected citizen along Fatmawati to Lebak Bulus area, South Jakarta refused to sell the land to Jakarta Provincial Government because the compensation money are not suitable with the wishes of the citizens.

We have allocated based on survey as much as Rp 35 million per meter, but they asked Rp 40 million per meter

Acting Jakarta Governor, Basuki Tjahaja Purnama, said there are more 100 lands owned by the citizen around Fatmawati to Lebak bulus that must be acquitted. But the acquisition of the land is obstructed because the owners ask higher compensation than the price set by the government based on the results of the survey.

"We have allocated based on survey as much as Rp 35 million per meter, but they asked Rp 40 million per meter," Basuki said in a meeting at City Hall, Friday (11/14).

Motorcycle is Restricted Passing Jalan Medan Merdeka Barat-HI

Basuki added that those lands will be used as MRT station and shelters.

"The negotiation is still running, but if the agreement can not be reached, we will give this case to the court. Please sue us in the court," Basuki uttered.

Basuki's firm stance is reasonable since the project can not be delayed. "We would lose Rp 500 billion if the project is one month late. Our target is completed in 2018," Basuki stated.

Linked News
Popular News indeks
  1. Free Additional Nutritious Food Distributed to 31 Toddlers in Kalibata

    access_time13-09-2024 remove_red_eye1144 personTiyo Surya Sakti
  2. Jakarta Women's Football Team Ready to Face West Java at PON XXI Final

    access_time13-09-2024 remove_red_eye843 personFolmer
  3. Water Channel Dredging on Bendungan Melayu Reaches 50 Percent

    access_time18-09-2024 remove_red_eye816 personAnita Karyati
  4. Jakarta Leads Medal Standing at PON XXI

    access_time17-09-2024 remove_red_eye770 personFolmer
  5. PON XXI Temporary Standings: Jakarta Continues to Shadow East Java

    access_time13-09-2024 remove_red_eye750 personAldi Geri Lumban Tobing